Fort Lewis

Fort Lewis Brigade Complex

Brigade Complex

Ft. Lewis, Washington

LEED® Project

The Ft. Lewis FY 07 Brigade Complex project consists of three separate projects—the Headquarters Building, the Barracks, and the Remote Switching Unit (RSU) Building. The new Headquarters is a 2-story, 17,477-SF office/classroom building. The new Barracks facility is 219,600 SF of condo-style military housing with approximately 306 housing units and associated common spaces. The RSU project is a 1,192-SF addition to an existing single-story 1,700-SF computer data center.

EEI’s services included the commissioning of all energy-using equipment associated with the Headquarters and Barracks buildings, and the new equipment being added to the RSU building.

 

Owner U.S. Army
Commissioning Authority Engineering Economics, Inc.
Area 238,777 SF
Total Construction Cost $73.8 Million

 

 
 

copyright © 2012, Engineering Economics, Inc.